Wuhan-Dalian Expressway

Project Information:

Project Date:September 2020

Project Location:Hubei

Project Name:Wuhan-Dalian Expressway

Project Solution:3,760t of trestles

Introduction:
The 527.189m (widening section of 111.490m + steel trestle bridge section of 316.975m + subgrade section of 69.524m) long Hankou North Interconnection Trestle Bridge starts at A2K0+000 and ends at A2K0+527.189. 3,760t of steel and 2,800m3 of concrete for the steel trestle bridge, and service life of 3 years.