Yudai River Basin Regulation Project

Project Information:

Project Date:July 2016

Project Location:Tongling

Project Name:River improvement project

Project Solution:139t of 4# 12m and 15m Lassen piles and 100t of Φ609 steel support and Φ400 splicing steel purlin

Introduction:
The Yudai River Watershed Improvement Project consists of 2 bidding sections. Main construction content includes: a new 1.06km side ditch of Yudai River beneath Nanhu Road Fast Lane; dredging of a 2.2km section of Yudai River; a new 9,000m3 storage pond for Chengguan Drainage Station; a new rainwater and sewage lift pump station; replacement of the connection gates between Tianjing Lake and Yudai River; migration of pipelines in the region and demolition of offices and residences of 7,353m2. Upon completion, municipal pipeline network of sewage and wastewater drainage along the route will be further improved.